Lock Out Tag Out (LOTO) Procedures Malaysia: Requirements, Steps & Compliance Guide
Comprehensive guide to lockout tagout (LOTO) procedures in Malaysia covering the 6-step LOTO process, hazardous energy types, DOSH requirements, equipment standards, training obligations, and common violations that lead to accidents. Published Date: 2026-02-14

Unexpected machinery startup during maintenance is one of the leading causes of workplace fatalities and amputations in Malaysian factories. Every year, workers are killed or seriously injured because equipment was not properly isolated before service work began. Lock Out Tag Out (LOTO) is the procedure that prevents this.
This guide explains the complete LOTO framework for Malaysian workplaces: every step of the procedure, every type of hazardous energy you must control, and the compliance requirements that DOSH inspectors check during audits.
This guide covers:
- What LOTO is and why it's required in Malaysia
- The 6-step LOTO procedure
- Types of hazardous energy requiring isolation
- LOTO equipment and device requirements
- Authorised, affected, and other employee roles
- Training requirements
- DOSH inspection points and common violations
- Insurance implications of LOTO failures
Disclaimer: This article provides general guidance based on the Occupational Safety and Health Act 1994 (amended 2022) and DOSH guidelines on control of hazardous energy as of February 2026. Regulations may be amended. Always verify current requirements with DOSH or qualified professionals before making compliance decisions.
What Is Lock Out Tag Out (LOTO)?
Lock Out Tag Out (LOTO) is a safety procedure that ensures machinery and equipment are properly shut down, isolated from all energy sources, and verified as de-energised before any maintenance, servicing, or repair work begins. The "lockout" component uses physical locking devices to prevent energy sources from being re-activated. The "tagout" component uses warning tags to communicate that equipment is being serviced and must not be operated.
LOTO is not just for electrical isolation. It applies to every form of hazardous energy: electrical, mechanical, hydraulic, pneumatic, thermal, chemical, and gravitational. A machine that's electrically isolated but still has pressurised hydraulic lines or stored mechanical energy can kill just as effectively.
| Aspect | Details |
|---|---|
| Purpose | Prevent unexpected startup or release of stored energy during maintenance |
| Legal basis (Malaysia) | OSHA 1994 Section 15 (general duty of employer); DOSH guidelines on control of hazardous energy |
| Applies to | All workplaces with machinery, equipment, or systems that could release hazardous energy |
| Industries most affected | Manufacturing, construction, oil and gas, power generation, food processing, chemical plants |
| DOSH enforcement | DOSH has published infographics and guidelines on LOTO; commonly checked during inspections |
Types of Hazardous Energy
Before you can lock out any machine, you need to identify every type of energy it uses, stores, or can release. Most serious LOTO failures happen because someone forgot about a secondary energy source. A CNC machine isn't just electrical; it may have hydraulic clamps, pneumatic actuators, and thermal energy from heated components.
| Energy Type | Sources | Isolation Method | Stored Energy Check |
|---|---|---|---|
| Electrical | Mains supply, generators, batteries, capacitors, UPS systems | Circuit breaker lockout, fuse removal, disconnect switch | Voltage tester at point of work; discharge capacitors |
| Hydraulic | Hydraulic presses, lifts, injection moulding, actuators | Valve lockout, pump isolation, bleed lines | Bleed pressure to zero; lower raised components; verify with pressure gauge |
| Pneumatic | Compressed air systems, air tools, pneumatic cylinders, air brakes | Valve lockout, compressor isolation, bleed valves | Bleed all lines to zero pressure; verify with pressure gauge |
| Mechanical | Springs, flywheels, rotating shafts, conveyor belts, gears | Block movement, release springs, engage mechanical locks/pins | Wait for rotating parts to stop; block against movement; release stored spring tension |
| Gravitational | Raised loads, suspended platforms, elevated machine parts, hydraulic rams | Lower to ground or mechanically block in position | Block or crib raised components; never rely solely on hydraulics to hold position |
| Thermal | Heated dies, ovens, steam systems, heat exchangers, molten materials | Isolate heat source, allow cool-down period | Temperature measurement before contact; allow adequate cooling time |
| Chemical | Process chemicals, gas lines, reactive materials, corrosive liquids | Valve lockout, blind flanges, double block and bleed | Purge lines; gas test atmosphere; verify with detector |
The 6-Step LOTO Procedure
The LOTO procedure follows a specific sequence. Skipping steps or changing the order creates gaps that lead to accidents. Every step must be completed before the next begins.
| Step | Action | Details |
|---|---|---|
| 1. Preparation | Identify all energy sources | Review the equipment-specific LOTO procedure. Identify every energy type (electrical, hydraulic, pneumatic, mechanical, gravitational, thermal, chemical). Locate all isolation points. Notify all affected employees that lockout is about to begin. |
| 2. Shutdown | Normal shutdown of equipment | Use the normal operating controls to shut down the machine in an orderly manner. Do not just pull the breaker. An orderly shutdown prevents additional hazards from abrupt stoppage (e.g., material jams, pressure surges). |
| 3. Isolation | Isolate all energy sources | Operate each energy isolating device to disconnect the equipment from every energy source. Turn breakers off, close valves, disconnect supply lines. Apply lockout devices (padlocks) and tags to each isolation point. |
| 4. Stored energy dissipation | Release or block all residual energy | Bleed hydraulic and pneumatic lines. Discharge capacitors. Block raised components. Release spring tension. Allow heated parts to cool. Purge chemical lines. This step is the most commonly skipped and the one that causes the most accidents. |
| 5. Verification | Verify zero energy state | Try to start the equipment using normal controls (press start button). It should not start. Test with voltage tester, pressure gauge, or other instruments. Verify that all moving parts have stopped. Only after verification is complete should anyone enter the danger zone. |
| 6. Perform work | Carry out maintenance/service | Perform the required maintenance or repair. Keep lockout devices in place throughout the entire duration of work. If work extends across shifts, conduct shift transfer lockout (outgoing crew removes their locks only after incoming crew applies theirs). |
Restoration Procedure (Re-Energisation)
When work is complete, the restoration process is just as important as the lockout. Premature removal of locks has caused fatal incidents.
| Step | Action |
|---|---|
| 1 | Inspect the work area: remove all tools, parts, and debris from the machine |
| 2 | Replace all machine guards, covers, and safety devices |
| 3 | Verify all workers are clear of the danger zone; conduct headcount |
| 4 | Notify all affected employees that locks are being removed and equipment is about to restart |
| 5 | Each authorised person removes their own lock and tag (only the person who applied it) |
| 6 | Re-energise equipment in controlled sequence; test operation before returning to production |
LOTO Equipment and Devices
LOTO requires specific physical devices. Using improvised locks, cable ties, or duct tape is not acceptable. Each authorised employee must have their own personal padlock that cannot be duplicated.
| Device | Application | Requirements |
|---|---|---|
| Safety padlock | Primary lockout device for breakers, valves, switches | Unique key (no master key); colour-coded by department; durable; corrosion-resistant |
| Lockout hasp | Allows multiple workers to lock out the same isolation point | Accommodates 6+ padlocks; cannot be removed until all locks are removed |
| Circuit breaker lockout | Prevents breaker from being switched on | Must fit the specific breaker type; universal and adjustable types available |
| Valve lockout | Gate valves, ball valves, butterfly valves | Size-matched to valve; holds valve in closed position; adjustable types for various diameters |
| Plug lockout | Electrical plugs, air line connectors | Encloses the plug to prevent reconnection |
| Lockout tags | Warning identification at every lockout point | Name of authorised person, date, reason, expected duration; non-reusable cable ties; weather-resistant |
| Lockout station/box | Centralised storage for all LOTO devices | Visible location near equipment; stocked with appropriate devices; inventory managed |
Roles and Responsibilities
LOTO programmes define three categories of employees. Each has different obligations and training requirements. Confusing these roles is a common cause of LOTO programme failure.
| Role | Definition | Responsibilities |
|---|---|---|
| Authorised employee | Person who applies lockout devices and performs the maintenance work | Executes the full LOTO procedure; applies personal lock and tag; verifies zero energy; removes own lock upon completion |
| Affected employee | Person who operates or uses the equipment being locked out | Must be notified before lockout begins and before equipment is re-energised; must not attempt to restart locked-out equipment |
| Other employees | Anyone who works in the area where LOTO is applied | Must recognise lockout devices and tags; must never tamper with or remove any lock or tag; must understand the purpose of LOTO |
Only the person who applied a lock may remove it. This is the most important rule in LOTO. No supervisor, no manager, no one else should remove another person's lock. If the person is unavailable, there must be a documented procedure for authorised lock removal that includes verification, notification, and management approval.
Equipment-Specific LOTO Procedures
Generic LOTO training isn't enough. Every machine or system that requires LOTO must have its own equipment-specific procedure documented and available at the point of use. This procedure maps every energy source and isolation point for that specific equipment.
| Element | What to Document |
|---|---|
| Equipment identification | Machine name, ID number, location, manufacturer, model |
| Energy sources | List every energy type with specific source (e.g., "480V 3-phase from MDB Panel 3, Breaker 12") |
| Isolation points | Location of each isolation device with physical description and photo |
| Lockout devices required | Type and size of lockout device for each isolation point |
| Stored energy | What residual energy exists and how to dissipate it (bleed points, blocking positions) |
| Verification method | How to verify zero energy state (try start button, voltage tester, pressure gauge) |
| Special precautions | Any unique hazards (e.g., "capacitor bank retains charge for 5 minutes after isolation") |
Common LOTO Scenarios in Malaysian Workplaces
| Scenario | Energy Types Involved | Key Risk |
|---|---|---|
| Clearing a jammed conveyor belt | Electrical, mechanical (stored tension in belt) | Belt snaps back when jam clears; motor restarts if not locked out |
| Servicing a hydraulic press | Electrical, hydraulic, gravitational | Ram drops under gravity if hydraulic pressure released without blocking |
| Cleaning inside a mixer/blender | Electrical, mechanical (rotating blades) | Blades activated by remote start; multiple start points possible |
| Replacing heating elements in an oven | Electrical, thermal | Residual heat causes burns; electrical shock from live wiring |
| Repairing a compressed air system | Pneumatic, mechanical | Stored air pressure in lines, receivers, and tools can cause projectile injuries |
| Working on process piping (chemical plant) | Chemical, thermal, pneumatic/hydraulic | Residual chemicals in lines; requires double block and bleed |
| Maintenance on overhead crane | Electrical, gravitational, mechanical | Crane movement while worker on structure; load drop from hoist |
Training Requirements
LOTO training is not a one-time event. Different employees need different levels of training, and refresher training is required annually and whenever procedures change.
| Training Type | Who Needs It | Content | Frequency |
|---|---|---|---|
| Authorised employee training | Maintenance technicians, electricians, mechanics | Full LOTO procedure, energy identification, equipment-specific procedures, verification methods, lockout device usage | Initial + annual refresher |
| Affected employee training | Machine operators, production workers | Purpose of LOTO, recognising lockout devices, prohibition against restarting locked-out equipment | Initial + annual refresher |
| Other employee awareness | All workers in LOTO areas | Recognise lockout devices, never interfere with locks or tags | Initial + as needed |
| Supervisor training | Production supervisors, shift leaders | Enforcing LOTO compliance, authorised lock removal procedure, incident investigation | Initial + annual refresher |
Group and Shift-Transfer Lockout
Large maintenance activities often involve multiple workers across different trades. Group lockout procedures ensure everyone's safety when several authorised persons work on the same equipment or system.
| Situation | Procedure |
|---|---|
| Multiple workers, same equipment | Use lockout hasp at each isolation point; each worker applies their personal lock to the hasp. Equipment cannot be re-energised until every lock is removed. |
| Shift changeover | Incoming crew applies their locks before outgoing crew removes theirs. There must never be a gap where no locks are in place. Conduct face-to-face handover. |
| Contractor workers | Contractors must use their own locks (distinct colour from facility locks). Facility coordinator and contractor supervisor both apply locks. Coordinate through permit-to-work system. |
DOSH Inspection Points for LOTO
LOTO compliance is a common focus during DOSH factory inspections. Inspectors look for both documentation and physical evidence of a functioning LOTO programme.
| What DOSH Inspectors Check | Evidence Required |
|---|---|
| Written LOTO programme | Documented policy, procedures, and scope of the programme |
| Equipment-specific procedures | Procedure sheets at or near each machine requiring LOTO |
| Training records | Documented initial and refresher training for authorised, affected, and other employees |
| LOTO devices available | Adequate supply of locks, tags, hasps, and specific lockout devices at lockout stations |
| Periodic inspections (audits) | Annual LOTO programme audit records; observation of authorised employees performing LOTO |
| Physical evidence during inspection | If maintenance is ongoing: locks and tags in place, isolation verified, workers following procedure |
Common LOTO Violations and Their Consequences
| Violation | Why It Happens | Potential Consequence |
|---|---|---|
| No LOTO applied ("quick fix" mentality) | Time pressure, "it'll only take a minute" | Amputation, crushing, electrocution, death |
| Not isolating all energy sources | Incomplete understanding of equipment; no equipment-specific procedure | Unexpected movement from stored hydraulic/pneumatic/gravitational energy |
| Skipping verification step | Overconfidence; assuming isolation is complete | Live equipment entered; wrong breaker isolated (similar-looking switches) |
| Removing someone else's lock | Worker absent; pressure to restart production | Equipment restarted while person still working inside; catastrophic injury |
| Using tags only (no locks) | Lockout devices not available; convenience | Tags can be ignored or removed; no physical prevention of re-energisation |
| No shift-transfer procedure | Maintenance spans shifts without handover protocol | New shift removes locks and re-energises while previous crew's worker is still inside |
Penalties for Non-Compliance
Malaysia doesn't have a standalone LOTO regulation, but LOTO compliance falls under the employer's general duty under Section 15 of OSHA 1994. Failure to implement LOTO where it's needed is a failure to provide a safe workplace.
| Offence | Penalty (OSHA 1994, Post-Amendment 2022) |
|---|---|
| Failure to ensure safety of employees (Section 15) | Fine up to RM500,000 or imprisonment up to 2 years, or both |
| Failure to provide safe system of work (Section 15) | Fine up to RM500,000 or imprisonment up to 2 years, or both |
| Failure to provide information, instruction, training (Section 15) | Fine up to RM500,000 or imprisonment up to 2 years, or both |
| Death caused by negligence (Penal Code Section 304A) | Imprisonment up to 2 years or fine, or both; director/officer personal liability possible |
For more on the full OSHA 1994 penalty framework, see our detailed guide.
Insurance Implications of LOTO Failures
LOTO failures result in some of the most severe workplace injuries: amputations, crush injuries, electrocutions, and fatalities. These generate the largest workmen compensation claims and can trigger CGL/employer's liability lawsuits.
| Insurance Impact | Details |
|---|---|
| Workmen compensation claims | Amputation and fatal injuries attract maximum compensation amounts; multiple victims possible |
| Employer's liability claims | Absence of LOTO programme is strong evidence of employer negligence in common law suits |
| Machinery breakdown claims | Damage to equipment during improper maintenance may not be covered if LOTO wasn't followed |
| Premium increases | Poor claims history from LOTO-related incidents increases premiums at renewal |
| Coverage disputes | Insurers may argue non-compliance with safety standards as a basis for coverage limitations |
LOTO Programme Compliance Checklist
| Item | Yes/No |
|---|---|
| Written LOTO policy and programme documented | |
| Equipment-specific LOTO procedures created for all machines requiring lockout | |
| All energy sources identified and documented for each machine | |
| Adequate LOTO devices (locks, tags, hasps, specific lockouts) available and stocked | |
| Authorised employees trained and records documented | |
| Affected and other employees trained on LOTO awareness | |
| Group lockout and shift-transfer procedures in place | |
| Contractor LOTO coordination procedure documented | |
| Authorised lock removal procedure documented (for absent workers) | |
| Annual LOTO programme audit conducted | |
| Annual refresher training completed for all relevant employees |
FAQ
Is LOTO a legal requirement in Malaysia?
Yes. While Malaysia doesn't have a standalone LOTO regulation, the requirement falls under Section 15 of OSHA 1994, which requires employers to provide a safe system of work. DOSH guidelines, the ICOP for safe maintenance, and industry standards all specify LOTO as the required method for controlling hazardous energy during maintenance. DOSH actively checks for LOTO compliance during inspections.
What are the 6 steps of LOTO?
Preparation (identify all energy sources), shutdown (orderly equipment stop), isolation (disconnect all energy sources and apply locks/tags), stored energy dissipation (release residual energy), verification (confirm zero energy state by attempting startup), and perform work (carry out maintenance with locks in place). Each step must be completed in order before proceeding to the next.
Who can apply and remove LOTO locks?
Only authorised employees who have completed full LOTO training can apply lockout devices. Only the person who applied a specific lock can remove it. If that person is unavailable, a documented authorised lock removal procedure must be followed, which typically requires management authorisation, attempts to contact the absent worker, and verification that the equipment is safe before removal.
What types of energy require LOTO?
All forms of hazardous energy: electrical, hydraulic, pneumatic, mechanical, gravitational, thermal, and chemical. A single machine may have multiple energy types. All must be identified, isolated, and verified before work begins. The stored energy dissipation step addresses residual energy that remains even after the source is disconnected.
How often should LOTO training be conducted?
Initial training before any employee is authorised to perform LOTO, with annual refresher training thereafter. Additional training is required when procedures change, new equipment is introduced, or audit findings reveal deficiencies. Training must be documented with attendance records, content covered, and competency verification.
Can tags be used without locks?
Tags alone should only be used when the energy isolating device is physically incapable of accepting a lock. In that case, additional safety measures must be implemented (e.g., removing a circuit element, blocking a valve). Tags warn but don't physically prevent re-energisation. Wherever possible, use locks and tags together.
What is group lockout?
Group lockout is used when multiple workers perform maintenance on the same equipment. A lockout hasp is placed at each isolation point, and every authorised worker applies their personal lock to the hasp. The equipment cannot be re-energised until every individual lock is removed. A designated authorised employee typically coordinates group lockout activities.
How does LOTO relate to permit-to-work systems?
LOTO is often integrated into the permit-to-work (PTW) system. A work permit may require LOTO as a precondition before the permit is issued. The permit documents what LOTO has been applied, by whom, and on which equipment. This is especially common in confined space entry and hot work permits.
What happens if a LOTO failure causes a fatality?
DOSH will investigate. Under OSHA 1994 (post-Amendment 2022), fines can reach RM500,000. Criminal prosecution under the Penal Code (Section 304A, causing death by negligent act) is also possible, with personal liability for directors and officers. Workmen compensation claims and civil lawsuits from the victim's family will follow. Absence of a LOTO programme is treated as evidence of employer negligence.
How often should LOTO programmes be audited?
At least annually. The audit should include direct observation of authorised employees performing LOTO on actual equipment, review of documentation, verification of training records, and inspection of lockout devices and stations. Audit findings must be documented and corrective actions implemented within a specified timeframe.
Foundation Conclusion
LOTO is one of the most effective ways to prevent serious workplace injuries during maintenance. It costs relatively little to implement compared to the cost of a single amputation or fatality. Every factory and construction site in Malaysia with powered equipment needs a documented LOTO programme.
LOTO failures generate severe injury claims that directly affect your workmen compensation and machinery breakdown insurance costs. A functioning LOTO programme demonstrates safety management maturity that insurers value when assessing your risk profile.
Talk to our risk specialists about workplace liability and machinery coverage
Unlock Exclusive Foundation Content
Subscribe for best practices,
research reports, and more, for your industry
Want to contact Foundation for your risk or insurance needs?
Insights on Property & Engineering Risks
Practical guidance on construction, industrial, and engineering insurance in Malaysia
Let’s Work Together
If you're managing a construction project, industrial facility, or commercial property in Malaysia and need insurance coverage, we can help structure a program that works.